ACTIVE RECEPTION ZONE FOR COVID-19 PATIENTS - TRUNG VUONG HOSPITAL
Item : Construction and finishing for the expansion area of Trung Vuong hospital
Location : No. 266 Ly Thuong Kiet, Ward 14, District 10, HCMC
Project have a scale of 50 hospital beds, including 42 beds for intensive care with the new model of "separating" the hospital with an isolated entrance to ensure safety. Doctor Nguyen Van Vinh Chau, Deputy Director of Ho Chi Minh City Department of Health, stated that the split model of Trung Vuong Hospital is very suitable for the strategy of adapting to nCoV in the new situation. The project was built on the 560 m2 large parking area of the hospital, started from September 7, 2021 and completed the basic construction after only 4 weeks of construction. Up to now, the basic department has been completed with all the necessary equipment to treat Covid-19.